Consider the data used in Example of a CUSUM Chart, where the machine fills 8-ounce cans of engine oil. In order to cut costs, the manufacturer is now concerned about significant over-filling (and not so concerned about under-filling). Use a one-sided CUSUM chart to identify any instances of over-filling. Anything that is 0.25 ounces beyond the mean of 8.1 is considered a problem.
1.
Select Help > Sample Data Library and open Quality Control/Oil1 Cusum.jmp.
2.
Select Analyze > Quality And Process > Control Chart > CUSUM.
3.
Deselect Two Sided.
4.
Select weight and click Process.
5.
Select hour and click Sample Label.
6.
Click H and type 0.25.
7.
Click Specify Stats.
8.
9.
10.
11.
One-Sided CUSUM Chart for Oil1 Cusum.jmp Data